                                                      Top view of ABC Verdun





          ABC VERDUN


          MALL, LEBANON




          A VIBRANT COMMUNITY HUB
          LEED certified ABC Verdun Mall
          in Beirut, Lebanon, was a deeply
          complex undertaking which had to
          be delivered in just 28.5 months.
          In order to meet this squeezed
          timeframe, in our role as design
          and supervision lead, we switched
          the structural design to precast.
          Corollary, manpower levels and
          costs were reduced on site, while
          during the construction stage we set
          up an authority-approved delivery
          and traffic management plan to
          ensure timely receipt of the precast
          components and zero disruption to
          local traffic. We drove the adoption
          of BIM from the project outset and
          through the operational phase (this
          was the first project in Lebanon
          to do so), thereby guaranteeing
          efficiencies throughout the entire
          asset lifecycle.